Update on underserved and high speed internet

The latest on the internet service coming to Reilly Township

 

The hold up is the that Comcast needs permission from the Railroad to cross their rail line by Mar Lin

The fiber optic lines are coming from Mar-Lin thru Llewellyn to Branchdale The person in charge of our project said it usually takes 90 days from RR for a reply.They have sent a letter asking for permission about 30 days ago

Hopefully they will reply in this time frame Sometimes the RR is in no hurry